Water/Wastewater Projects

Chris-Hill is a major water/wastewater contractor in Shelby County and the surrounding counties. Projects range from minor plant maintenance to entire new facility construction. 

New Pump Outflow Pipes
New Pump Outflow Pipes

press to zoom
New Pump Check Valves
New Pump Check Valves

press to zoom
Temporary Bypass Pumping
Temporary Bypass Pumping

press to zoom
New Pump Outflow Pipes
New Pump Outflow Pipes

press to zoom
1/4

Millington Wastewater Treatment Plant Screw Pump Replacement

The screw pump pumping system at Millington's wastewater pumping station was replaced with electric submersible pumps to keep up with increasing plant volume. 

Installation of New :Lagoon Cover
Installation of New :Lagoon Cover

press to zoom
Installation of Footers to Hold Down Lagoon Cover
Installation of Footers to Hold Down Lagoon Cover

press to zoom
Damaged Existing Lagoon Cover
Damaged Existing Lagoon Cover

press to zoom
Installation of New :Lagoon Cover
Installation of New :Lagoon Cover

press to zoom
1/4

Maxson WWTP Lagoon Cover Replacement

The damaged cover over a 20 acre wastewater lagoon in Memphis's Maxson WWTP was removed and replaced. 

Clean Wastewater Leaving the Plant
Clean Wastewater Leaving the Plant

press to zoom
Crack Repair
Crack Repair

press to zoom

press to zoom
Clean Wastewater Leaving the Plant
Clean Wastewater Leaving the Plant

press to zoom
1/5

Stiles Wastewater Treatment Plant Disinfection Tank Upgrades

Chris-Hill cleaned, repaired, and installed baffles in one of Memphis's two wastewater treatment plants as part of a major disinfection tank upgrade project.

Finished Clarifier
Finished Clarifier

press to zoom
Replaced One Screw Pump
Replaced One Screw Pump

press to zoom

press to zoom
Finished Clarifier
Finished Clarifier

press to zoom
1/4

Collierville Wastewater Treatment Facility

Two new 100 foot diameter wastewater clarifier tanks were installed as part of a complete plant expansion to increase wastewater plant capacity.

Final Tank Top Slab Concrete Pour
Final Tank Top Slab Concrete Pour

press to zoom
Installing Falsework for Top Slab Concrete Forms
Installing Falsework for Top Slab Concrete Forms

press to zoom
Bottom of Tank Slab and Soldier Pile Wood Lagging Shoring
Bottom of Tank Slab and Soldier Pile Wood Lagging Shoring

press to zoom
Final Tank Top Slab Concrete Pour
Final Tank Top Slab Concrete Pour

press to zoom
1/4

MLGW Mallory Pumping Station Washwater Recovery Basin

Chris-Hill installed a massive storage tank to help reuse water at one of Memphis's drinking water treatment plants.

Finished Tank and Protective Wall
Finished Tank and Protective Wall

press to zoom
Forming for Tank Wall and Foundation
Forming for Tank Wall and Foundation

press to zoom
Previous Existing Conditions
Previous Existing Conditions

press to zoom
Finished Tank and Protective Wall
Finished Tank and Protective Wall

press to zoom
1/5

Germantown Hypochlorite Tank Replacement

An existing chemical storage system for a drinking water treatment facility was replaced in Germantown, TN.

Finished Valve Replacement and Saddles
Finished Valve Replacement and Saddles

press to zoom
Helical Pier Installation
Helical Pier Installation

press to zoom
Previous Existing Conditions
Previous Existing Conditions

press to zoom
Finished Valve Replacement and Saddles
Finished Valve Replacement and Saddles

press to zoom
1/4

West Memphis Storm Water Pump Station Repair

Leaking valves on three 54 inch storm water pipes were removed and replaced. To prevent further settling of the pipes, helical piers and concrete saddles were installed under the pipes.

Finished Pumps
Finished Pumps

press to zoom
Installation of Pumps
Installation of Pumps

press to zoom
Working on the Pump Station
Working on the Pump Station

press to zoom
Finished Pumps
Finished Pumps

press to zoom
1/5

Johnson Creek Wastewater Treatment Facility Pump Station

Chris-Hill installed a 50 foot deep sewage pumping station in Desoto County, MS to increase wastewater plant treatment capabilities.